Procurement of Infrastructure FY-2020

Negotiated Procurement of Completion of Administration Building and Completion of Academic Building I

Date Posted: October 21, 2020   Closing Date: November 04, 2020 (2:45 PM)

ABC: Php 38,000,000.00

Remarks: On Going

 


Procurement of Infrastructure FY-2019

Rehabilitation of School Buildings

Date Posted: July 8, 2019   Closing Date: July 29, 2019 (9:45 AM)

ABC: Php 25,000,000.00

Remarks: Awarded to OCM Steel Corporation

Improvement of the Main Power Supply Cable at the Grandstand

Date Posted: October 29, 2019   Closing Date: November 18, 2019 (8:45 AM)

ABC: Php 2,185,201.86

Remarks: On-going

2019 MOOE_Grandstand Power Supply Cable BOQ Blank

2019 MOOE_Grandstand Power Supply Cable P2

2019 MOOE_Grandstand Power Supply Cable P1A

2019 MOOE_Grandstand Power Supply Cable P1

Bid Bulletin No.1, Improvement of the Main Power Supply Cable of the Grandstand

Bid Docs_Grandstand 2019 (2019-10-28)

 

Rehabilitation of School Building

Date Posted: October 15, 2018                         Closing Date: November 6, 2018 (8:45am) – Closed

ABC: Php25,000,000.00                                     Remarks:  Awarded to OCM Steel Corporation

[Bid Documents] [Bill of Quantities] [Section IV-Specification] [Plans and Drawing]

 

procurement of infrastructure FY-2018


Rehabilitation of Academic Building

Date Posted: October 15, 2018                         Closing Date: November 6, 2018 (8:45am) – Closed

ABC: Php3,300,000.00                                     Remarks:  Awarded to MZR Builders

[Bid Documents] [Bill of Quantities] [Section IV-Specification] [Plans and Drawing]


Negotiated Procurement (Adjacent & Contiguous) Rehabilitation of Residence Hall (Additional Works)

Date Posted: July 24, 2018                              Closing Date: August 1, 2018 (9:30am) – Closed

ABC: Php3,525,600.84                                     Remarks: Negotiated to OCM Steel Corporation

[Notice of Negotiation]


Negotiated Procurement (Adjacent & Contiguous) Site Development (Additional Works)

Date Posted: August 1, 2018                              Closing Date: August 8, 2018 (9:30am) – Closed

ABC: Php3,370,812.40                                        Remarks: Negotiated to OCM Steel Corporation

[Notice of Negotiation]


Rehabilitation of Residence Hall

Date Posted: April 7, 2018                                Closing Date: May 7, 2018 (9:45am) – Closed

ABC: Php17,628,000.00                                    Remarks: Awarded to OCM Steel Corporation

[Bid Documents] [Bid Bulletin No. 1] [Bill of Quantities] [Annex A1] [Annex A2] [Section VI-Specification] [Plans & Drawing]


Procurement of Infrastructure Projects for CY2018: (a) Site Development: Rehabilitation of the Guardhouse, Track and Field and Improvement of Campus Grounds; and (b) Installation of Main Power Supply Cable for the Residence Halls

Date Posted: March 17, 2018                              Closing Date: April 10, 2018 (8:30am) – Closed

ABC: Php21,650,000.00                                       Remarks: Awarded to OCM Steel Corporation

[Bid Documents] [Bid Bulletin No. 1] [Bill of Quantities] [Annex A1] [Annex A2] [Section VI-Specification] [Plans & Drawing]